Risk Management
- The art and science of identifying, analyzing, and responding to risk
The Challenger Mission 51L
- 10th mission for the Challenger Shuttle
- TISP – Teachers In Space Program
- Christa McAuliffe
- Politically Charged Launch
- Christa was to appear via television link during Reagan’s State of the Union Address in 1986
Challenger Delays
- Liftoff Initially Scheduled for 15:43 EST on Jan. 22, 1986
- Delays in 61-C mission pushed liftoff to Jan. 23, then Jan. 24
- Reset to Jan. 25 due to weather
- Postponed another day due to launch processing problems
- Rescheduled for 9:37 EST Jan. 27 due to weather
- Delayed again due to equipment failure for 24 hours
- Final 2 hour delay due to hardware interface module problems
The Challenger Disaster
73 Seconds After Liftoff
What Went Wrong??
Failure of an “O-ring” seal in the solid-fuel rocket on the Space Shuttle Challenger's right side
Flames cut into main liquid fuel tank
Four Main Causes of O-Ring Failure
- Pre-flight Leak Tests
- O-Ring Erosions
- Joint Rotation
- Low Temperatures
Poor Risk Management
- Risks were managed using Critical Items Lists
- Criticality 1-Loss of Life or Ship
- Criticality 2-Mission Aborted
- CIL Flaws
- Unreliable
- In previous missions, criticality1 issues occurred but loss of life/ship did not
- Negotiable
- Identified risks could later be waived
Known Potential Problems
O-rings were “Criticality 1” feature
O-ring seal failure on previous missions
Launch Constraint placed on subsequent launches
These constraints had been imposed and regularly waived by the SRB Project Manager